The project management field has the imperative to increase the project probability of success. Experts have developed several project management maturity models to assets and improve the project outcome. However, the current literature lacks of models allowing correlating the measured maturity and the expected probability of success. This paper uses the characteristics of Bayesian networks to formalize experts' knowledge and to extract knowledge from a project overcost database. It develops a m...